Office moves
Start with the internet line
The most common office-move problem is arriving at the new premises with no internet. Connectivity has the longest lead time of anything on the list, so it’s the first thing to order, ideally as soon as the lease is agreed.
Even standard broadband can need an engineer visit, especially in a building without a working line. A dedicated leased line, which many offices rely on, can take weeks or months, especially if new cabling has to be laid. Openreach, which builds most of the UK’s lines, lists needing permission from a landowner or the council, and having to build new network, among the usual causes of delay.
Our advice: start the conversation three months or more before the move, ask the landlord what’s already in the building, and have a 4G or 5G backup ready in case the line is late.
Phones
Phones and the 2027 switch-off
You can’t order a new traditional phone line any more. Openreach stopped selling new analogue lines across the UK in September 2023, and the old network is due to be switched off on 31 January 2027. A new office will get internet-based phones, which makes a move the natural moment to change the whole phone system.
It isn’t only the handsets. Alarms, door entry systems, lift emergency phones and card terminals can depend on the old lines, so they need checking before you move. We work alongside telecoms partners on lines and numbers. Our page on business phone systems has more.